The client asks for a different floor finish after the original materials have been ordered. The site supervisor agrees verbally. Three weeks later, the contractor sends an extra bill and the client asks who approved it.
The problem is not just a missing signature. A change affects scope, materials, labour, cost and often the schedule. Each party needs to see the same version before work is treated as agreed.
Record the change against the original scope
Start with the contract item, drawing revision or work package being changed. Give the request a unique number and record the site, requester, date and reason. Add photographs and marked-up drawings where they explain the difference. Avoid a description like “extra work at site” that cannot be compared with the original quote.
Separate a request from an approval. A supervisor may capture a site instruction, but the person authorised to accept a cost change may be the owner or a project manager. The workflow should show both roles clearly.
Autodesk's change order setup guidance describes distinct request and owner change order approval workflows, review statuses and supporting document requirements. A small contractor need not purchase a large platform to learn from that structure.
Estimate money and time before asking for approval
Show the added and removed quantities, unit rates, taxes where applicable and total difference. If the change delays a dependency, state the expected schedule effect and which assumptions the estimate depends on. A client may approve the design change but dispute the cost unless both are presented together.
For the floor finish example, compare the old and new material quantities, credit for reusable or cancelled stock, labour difference and any procurement lead time. Attach the supplier quote if it is part of the calculation. Mark the estimate as provisional when a site measurement is still pending.
Use explicit review states
Practical states include draft, submitted, needs revision, approved, rejected and closed. Every decision should record the actor, timestamp, version and any conditions. A rejected proposal should stay in the history rather than disappear; later disputes often depend on what was proposed and when.
Keep the approval record accessible to the site team before the work starts. If an emergency requires immediate safety work, record who authorised it and document the commercial decision as soon as possible. Do not silently label all work as approved because a message was read.
Start with a register, then automate the bottleneck
For a few projects, a shared register and signed approval document may be sufficient. A custom web or mobile workflow becomes useful when several sites, contractors and owners exchange revisions every day. It can link request numbers to drawings, send decision reminders, restrict who can approve, and export an auditable history for billing.
Before building, sample five past changes. Identify where each one lost context: unclear scope, missing cost detail, wrong approver or outdated drawing. At adityazen, I can turn those real gaps into a focused approval workflow for a construction team, without adding screens the site staff will not use.